The critical path for a project was found to be 37 days. The variances total 27. What is probability of completing in 43 days? Below is information that might be useful to answer the question. Answer to 2 decimal points

Answers

Answer 1

Answer:

0.1241.

Step-by-step explanation:

So, from the question we are given the following parameters or information or data which are going to help us in solving this particular question/problem. They are; [1]. The critical path for a project = 37 days, the variances total or variance of critical path or sum of variance on critical path]². = 27, the desired completion time/day = 43 days.

So, we will be making use of the formula given below;

The number of standard deviation = desired completion time/day - critical time or sum of critical path times ÷√[variance of critical path or sum of variance on critical path]².

The number of standard deviation = 43 - 37 ÷ √27 = 1.1547.

Thus, the probability of completing in 43 days = P(Z > 1.1547) = 0.1241.


Related Questions

Ellie the elephant has some peanuts. She eats up 49 peanuts. Now Ellie the elephant has 31 peanuts. How many peanuts did she have before?

Answers

Answer:

80

Step-by-step explanation:

do: 49+31=Your answer

Ellie had 80 peanuts before she ate 49 of them.

What is Equation?

Two or more expressions with an Equal sign is called as Equation.

Let x be the number of peanuts Ellie had before she ate 49 of them.

After eating 49 peanuts, Ellie has 31 peanuts left, so we can write an equation:

x - 49 = 31

To solve for x, we add 49 to both sides of the equation:

x - 49 + 49 = 31 + 49

Simplifying, we get:

x = 80

Therefore, Ellie had 80 peanuts before she ate 49 of them.

To learn more on Equation:

https://brainly.com/question/10413253

#SPJ2

how can you plot,compare,and order rational numbers using a number line?

Answers

Just as positive and negative integers can be represented on a number line, so can positive and negative rational numbers. You can use a number line to help you compare and order negative rational numbers. Graph the decimals on a number line. Since -1.2 is to the left of 0.8, -1.2 < 0.8.

5 of 10
Which of the following are one-dimensional figures?
Check all that apply.
O A. Segment
B. Ray
O C. Angle
O D. Line
D E. Plane
F. Cube
Its (Ray , Segment, line, )

Answers

Segment, ray and line are one-dimensional figures.

We need to check from the given options which are one-dimensional figures.

What are one-dimensional figures?

One-dimensional: Only a single measurement is possible for a one-dimensional figure. A line segment drawn on a surface is a one-dimensional object, as it has only length and no width.  

Here, the segment is a one-dimensional figure.

Ray is a one-dimensional figure.

Angle is a two-dimensional figure.

A line is a one-dimensional figure.

The plane is a two-dimensional figure.

A cube is a three-dimensional figure.

Therefore, segment, ray and line are one-dimensional figures.

To learn more about one-dimensional figures visit:

https://brainly.com/question/17967616.

#SPJ2

Please help me solve What is m

Answers

Answer:

a=60

b=85

c=35

Step-by-step explanation:

a is shown to be 60 in the text along with c being 85 with its angle so just add 60 and 85 to get 145 and fill in the remaining to get 180 which gives you c as 35

Suppose the horses in a large stable have a mean weight of 975lbs, and a standard deviation of 52lbs.What is the probability that the mean weight of the sample of horses would differ from the population mean by less than 15lbsif 31horses are sampled at random from the stable

Answers

Answer: The required probability = 0.8926

Step-by-step explanation:

Given: [tex]\mu=975\text{ lbs}[/tex],  [tex]\sigma= 52\text{ lbs}[/tex]

Let x = weight of horse stable.

Sample size : n= 31

Then, the probability that the mean weight of the sample of horses would differ from the population mean by less than 15 will be:

[tex]P(-15<P(\overline{x}-\mu)<15)=P(\dfrac{-15}{\dfrac{52}{\sqrt{31}}}<\dfrac{\overline{x}-\mu}{\dfrac{\sigma}{\sqrt{n}}}<\dfrac{15}{\dfrac{52}{\sqrt{31}}})\\\\=P(-1.61<z<1.61)\ \ \ [z=\dfrac{\overline{x}-\mu}{\dfrac{\sigma}{\sqrt{n}}}]\\\\=2(z<1.61)-1\ \ \ [P(-z<Z<z)=2(Z<z)-1]\\\\=2( 0.9463)-1\\\\=0.8926[/tex]

Hence, the required probability = 0.8926

light travels 3 x 10^5 kilometers in one second. how far does it travel in 7.6 seconds?

Answers

Answer:

1800000 kilometers

Step-by-step explanation:

i think im not 100% sure

Pls helpppppp this stuff makes no sense

Answers

Answer:

x = 5

Step-by-step explanation:

a || b and a line intersecting them is their transversal.

[tex] \therefore m\angle 1=m\angle 5\\(corresponding \:\angle 's) \\\\

\therefore 60 - 2x = 70 - 4x\\\\

\therefore 4x - 2x = 70 - 60\\\\

\therefore 2x = 10\\\\

\therefore x =\frac{10}{2} \\\\

\huge \orange {\boxed {\therefore x = 5}}[/tex]

***PLEASE HELP*** What is the remainder in the synthetic division problem below??

Answers

Answer:

A. 4

Step-by-step explanation:

1      1  2  -3  3

           1   3  0

       1   3  0  3

Bring down the first coefficient, 1 and multiply it to 1 and that will be 1

Put the result below 2 and add 2 and 1, that would be 3

Multiply 3 and 1, that would be 3. Put it below -3.

Add -3 and 3 that would be 0.

Multiply 0 and 1, that would be 0. Put 0 below 3.

Add 3 and 0 then that would be 3.

Since the final result is 3, the remainder is 3.

(Sorry for the mistake earlier ;-;)

On day 3 of a canned food drive, the students had collected 80 cans and were 40% of the way to their goal. What was their goal for the total number of cans they hoped to collect?

Answers

Answer:

200 cans

Step-by-step explanation:

use rate method

80         40

x           100

40x=8000

x=8000/40

x=200

Given m|n, find the value of x.
t
xo
>m
53°

Answers

Answer:

32 degrees goto the x vaule

Andy was at Level –1 and took the elevator to Level 21. How many levels did the elevator move upward?

Answers

Answer: 22 Levels

Step-by-step explanation: He would need to go one level higher just to get to level one, and another 21 to get to the level that he wants to, so the total would be 22 levels.

Answer:

The elevator moved up 21 levels

A small town has two local high schools. High School A currently has 750 students

and is projected to grow by 75 students each year. High School B currently has 900

students and is projected to grow by 25 students each year. Let A represent the

number of students in High School A in t years, and let B represent the number of

students in High School B after t years. Write an equation for each situation, in terms

of t, and determine how many students would be in each high school in the year they

are projected to have the same number of students.

Ok

Answers

Answer:

A=750 +75*t

B=900 +25*t

There would be 975 students in each high school in year 3 when they are expected to have the same number of students.

Step-by-step explanation:

You know that High School A currently has 750 students  and is projected to grow by 75 students each year.   With A being the number of students in High School A in t years, this number will be the number of students it has initially added to the number of students who have joined after t years. This is represented by:

A=750 +75*t

You know that High School B currently has 900 students  and is projected to grow by 25 students each year.   With B being the number of students in High School B in t years, this number will be the number of students it has initially added to the number of students who have joined after t years. This is represented by:

B=900 +25*t

You want to determine how many students there would be in each high school in the year that they are projected to have the same number of students. That is, in year t the number of students is the same, so

A = B

750 +75*t=900 + 25*t

Solving:

75*t -25*t= 900 - 750

50*t= 150

[tex]t=\frac{150}{50}[/tex]

t=3

This indicates that in year 3 both High Schools are projected to have the same number of students. To get that amount, you simply replace this value in the expressions:

A=750 +75*t= 750 +75*3= 975

B=900 + 25*t=900 + 25*3= 975

There would be 975 students in each high school in year 3 when they are expected to have the same number of students.

Answer: REAL ANSWER

A= 75t +750

B=25t +900

Answer: 975 students

The state of Tennessee is shaped like a parallelogram. Its approximate dimensions are a base of 440 miles and a height of 120 miles. The state of Colorado is shaped like a rectangle, with approximate dimensions of 385 miles long and 275 miles wide. Ted works for a geographical company that is working on finding the areas of each state in the Union. Ted asked an assistant to double‐check his answers. Approximate area of Tennessee: 63,000 mi2 Approximate area of Colorado: 106, 000 mi2 11. If you were Ted’s assistant, would you agree with his answers? Explain why you answered yes or no by showing your work and explaining how it helped you come to your answer.

Answers

Answer:

Tennessee area we don´t know there is something wrong

Colorado area is ok close to 106000 mi²

Step-by-step explanation:

Tennessee is shaped like a parallelogram base is equal to 440 miles and the height is 120 miles. Therefore

Ap = b*h  = 440 * 120   = 52800 mi²

But the area of Tennessee  is 63000 mi²

Then there is something wrong because difference in mi² is

10400 mi²

10400/ 63000 = 0,165 % faraway of the real number

In the case of Colorado

Ac = 385 * 275

Ac = 105875 mi²   pretty close to 106000 mi²

Then from double check in the areas, we conclude in a high difference in the figures for the state of Tennessee ( one or both of the figures are incorrect ). The state of Colorado area is oK

Una partícula se mueve sobre el eje x de acuerdo con la ecuación del movimiento
s=f(t) donde s es la distancia dirigida al origen en pies a los t segundos.
a) La velocidad v(t) y la aceleración a(t) en el instante t.
b) El instante t en el que la velocidad es cero.
s= 6t-t²
s=t²-6t
s= t²-9t+24

Answers

Answer:

a)

s= 6t-t² -->  v = 6 -2t  --> a = -2

s=t²-6t  --> v = 2t-6       -->    a = 2

s= t²-9t+24  -->  v = 2t -9   -->  a = 2

b)

v = 6 -2t  = 0  --> t = 3

v = 2t-6  = 0   --> t = 3

v = 2t -9   = 0 --> t = 9/2

Step-by-step explanation:

si s(t) es la distancia, la velocidad es la primera derivada v(t) = s'(t)

y la acceleracion es la segunda derivada : a(t)= v'(t) = s''(t)

s= 6t-t² -->  v = 6 -2t  --> a = -2

s=t²-6t  --> v = 2t-6       -->    a = 2

s= t²-9t+24  -->  v = 2t -9   -->  a = 2

The auxiliary equation for the given differential equation has complex roots. Find a general solution. y''-10y' 29y=0

Answers

Answer:

[tex]y = Acos5x - Bsin5x[/tex]

Step-by-step explanation:

Given the differential equation y''-10y'+29y=0

First, we need to rewrite it as an auxiliary equation as shown:

Let y'' = m²y and y' = my

Substitute the values into the general equation

m²y-10my+29y = 0

Factor out y:

(m²-10m+29)y = 0 [The auxiliary equation]

Solve the auxiliary equation and find the roots of the equation

m²-10m+29 = 0

m = -b±√(b²-4ac)/2a

a = 1, b = -10, c = 29

m = -10±√(10²-4(1)(29))/2(1)

m = -10±√(100-116)/2

m = -10±√-16/2

m = (-10±4i)/2

m = -10/2 + 4i/2

m = -5+2i

Comparing the complex number with a+bi, a = -5 and b = 2

The general solution for complex solution is expressed as:

[tex]y = Acosax + Bsinax[/tex]

Substitute the value of a in the equation

[tex]y = Acos(-5)x + Bsin(-5)x\\y = Acos5x-Bsin5x[/tex]

Hence the general solution to the differential equation is [tex]y = Acos5x - Bsin5x[/tex]

5,049 +48=105
MD Model with Mathematics A comic store sells two rare
comic books for $1,824. The price of one comic book is
11 times as much as the price of the other.
• 'Write an equation to model the price of the less expensive
comic book. Then find the price.
• Write an equation to model the price of the more expensive
comic book. Then find the price.

Answers

Solution (a) :-

Let the cost of the less expensive comic book be x .

Then :-

[tex]1284 - 11x = x[/tex]

Using this equation , we can find the cost of the less expensive comic book .

Price of the less expensive book :-

[tex]1284 - 11x = x[/tex]

[tex]11x + x = 1284[/tex]

[tex]12x = 1284[/tex]

[tex]x = \frac{1284}{12} [/tex]

[tex]x = 107[/tex]

Cost of the less expensive book is 107 .

Therefore , the epice of the less expensive book = $ 107 .

Solution (b) :-

Cost of the more expensive book = 11x

Which means :-

[tex]1284 - x = 11x[/tex]

[tex]11x + x = 1284[/tex]

[tex]12x = 1284[/tex]

[tex]x = 107[/tex]

[tex]11x = 11 \times 107[/tex]

[tex] = 1177[/tex]

Therefore , the price of the more expensive book = $ 1177 .

A random sample drawn from a population with mean μ= 66 and standard deviation σ= 6.

Required:
a. Comment on the sampling distribution of the sample mean with n = 16 and n = 36.
b. Can you use standard normal distribution to calculate the probability that the sample mean falls between 66 and 68 for both sample sizes?
c. Report the probability if you answered yes to the previous question for either sample size.

Answers

Answer:

In step by step explanation

Step-by-step explanation:

a) Normal distribution N( 0, 1 )

If the sample size is equal n = 16 we have to use t-student distribution since     n < 30.

In the case n = 36 we should use normal distribution (z tables)

b) We can´t use the  standard normal distribution to calculate the probability that the sample mean falls between 66 and 68 in the first case n < 30 .

We can calculate that  probability in the case of the second sample

4. Tell whether the equation is a linear equation.
4x-3y = 2

Answers

Answer:

What Is X and Y

Step-by-step explanation:

Answer:

It is a linear equation.

Step-by-step explanation:

It has no squares in the equation, meaning the line is straight, therefore meaning the equation is linear.

Which of the following is equal to −|−43|

-43

0

43

-(-43)

Answers

Answer:

i think ur answer is -43.i hope u get it

Answer:

the answer is i guess -43

Step-by-step explanation:

|-43| = 43

so -|-43| = -43

juan feeds his dog 2 scoops of dry dog food every day. each scoop weighs 1/3 pound. he bought a new 12 pound of dog food. how many days will it last​

Answers

The food will lash him 18 days.

Please help!!

Square ABCD has vertices A(-2,-3), B(4, -1), C(2,5), and D(-4,3). Find the length of a side

of the square. Round your answer to the nearest tenth if necessary.

Answers

Answer:

The length of a side of the square is 6.3 units.

Step-by-step explanation:

When given vertices for a given shape, the length of the side is calculated using the formula:

√(x2 - x1)² + (y2 - y1)²

When given vertices (x1 , y1) and (x2 , y2)

Square ABCD has vertices A(-2,-3), B(4, -1), C(2,5), and D(-4,3). Find the length of a side

Side AB : A(-2,-3), B(4, -1)

√(x2 - x1)² + (y2 - y1)²

= √(4 -(-2))² + (-1 -(-3))²

= √ 6² + 2²

= √36 + 4

= √40

= 6.3245553203

≈ 6.3 units

B(4, -1), C(2,5),

√(x2 - x1)² + (y2 - y1)²

= √ (2- 4)² + (5- (-1))²

= √-2² + 6²

= √4 + 36

= √40

= 6.3245553203

≈ 6.3 units

C(2,5), D(-4,3).

√(x2 - x1)² + (y2 - y1)²

= √(-4 - 2)² + (3 - 5)²

= √-6² + -2²

= √36 + 4

= √40

= 6.3245553203

≈ 6.3 units

A(-2,-3), D(-4,3).

√(x2 - x1)² + (y2 - y1)²

= √(-4 -(-2))² + (3 - (-3))²

= √-2² + 6²

= √4 + 36

= √40

= 6.3245553203

≈ 6.3 units

Multiply. Express your answer in simplest form. 9 1/6 × 1 1/11. A. 10 B. 9 1/66 C. 10 1/17 D. 10 5/6​

Answers

Answer:

9 1/66

Step-by-step explanation:

9 x 1 is 9 so its that but to add more proof the problem is 9 1/6, 1 1/11 multiply 6 and 11 it is 66 so the answer is 9 1/66

-2/3 - (-1 1/3)


A. -1 2/3
B. -2/3
C. -1/3
D. 2/3

Answers

Answer is 2/3

Hope this helps

Pendiente 6 y puntos (5, -2)

Answers

Answer:A HORLE

Step-by-step explanation:

In the diagram, the origin is at the center of a cube that has edges 6 units long. The x-, y-, and z-axes are perpendicular to the faces of the cube. Give the coordinates of the corner at point E.

(3, 3, –3)

(3, –3, –3)

(–3, 3, 3)

(–3, –3, 3)

Answers

Answer:

I really think that (3 , -3 , -3) is the answer but I could be wrong.

Step-by-step explanation:

I'm taking the quiz right now and from the graph it looks like point E is in the position (3 , -3 , -3).

Once again, sorry if I'm wrong.

What is
f(x) = x3 – 4x2 – 7x + 10 in factored form given that 5 is a zero of the function?

Answers

Answer:

(x-2)(x+1)(x-5)

Step-by-step explanation:

a baseball field is being constructed. the builders noticed that the batters would have the sun in their eyes when batting from point a. the builders decided to rotate the model 90 counterclockwise about the origin where is the new location of the batter?
A) E
B)F
C)G
D)H

Answers

Answer:

b

Step-by-step explanation:

Answer:

G

Step-by-step explanation:

Express 4/5 as a percent. Make sure to label your answer with %.

Answers

I’m pretty sure it’s 80%

The equation x + y = z relates the whole numbers x, y, and z. How does z compare to x? If it helps, consider an example where you substitute 3 for x, 5 for y, and 8 for z

Answers

Answer:

The equation x + y = z relates the whole numbers.

Hopefully, this helps! :D

Ask your question below!

What is the slope of the line passing through the points (0,-5) and (4,2)?


Enter your answer in the box

Answers

Answer:

[tex] \huge{ \boxed{ \tt{ \frac{ 7}{4} }}}[/tex]

Step-by-step explanation:

[tex] \text{Let \: the \: points \: be \: A \: and \: B}[/tex]

[tex] \sf{A \:( \: 0 \:, - 5 \: ) \longrightarrow{ \: (x1 \:, y1)}}[/tex]

[tex] \sf{B(4 \:, 2) \: \longrightarrow{ \:( x2 \:, y2)}}[/tex]

[tex] \underline{ \text{Finding \: the \: slope} }: [/tex]

[tex] \boxed{ \sf{Slope = \frac{y2 - y1}{x2 - x1}}} [/tex]

[tex] \sf{➳ \: Slope = \frac{2 - ( - 5)}{4 - 0}} [/tex]

[tex] \sf{➳ \: Slope = \frac{ 2 + 5}{4} }[/tex]

[tex] \sf{➳ \: Slope = \frac{7}{4} }[/tex]

[tex] \text{Hope \: I \: helped!}[/tex]

[tex] \text{Best \: regards!}[/tex]

~[tex] \text{TheAnimeGirl}[/tex]

Other Questions
A hospital administrator must cut of the staff due to budget cuts. If the hospital employs 875 people, how many people must be dismissed? Circle Ud. or t to indicate how you would address the person being spoken to.*TUsted1. "Hola, Sr. Gmez."2. "Buenos dias, Luis"3. "Cmo ests, Paco?"4. "Buenos tardes, profesor!"5. "Adis, seora."oI will make brainllest plz nobody who doesn't know how to solve these answer.show work2,4,6,8,10assig 9 is anyone willing to do my DIT tests for me? pls help me. A scuba diver descends 63 feet in 18 seconds.What integer represents the change in thedivers position in feet per second? What do you think it means to be a responsible citizen ? What was Walt Disney's original character? Write the equation of the line the that is parallel to 21x-7y=12 and goes through the point (1, -3). ben plays basketball every 6 times in 3 weeks. At this rate, how many times does he play basketball in 10 weeks The sentiment in this speech contributed to what difference between the New England and Southern colonies ? A. England colonies did not allow any form of slavery or indentured servitude Absolute advantage is best defined as: HELP!!! 3 SENTENCES PLEASE!!!how is the structure of DNA significant in the transfer of information? Why was the Brooklyn Bridge important to New York City? Choose the best answer.It would bring visitors to New York.It allowed easier access to the city.It was the eighth wonder of the world. Which is a major theme from The Land?O Power corrupts the people who have it.O Though they try, people are never truly free.Inequality hurts a wide variety of people.Tradition outweighs the progress of people. Knowledge Check 01 The difference between absorption costing net operating income and variable costing net operating income can be explained by the way these two methods account for ________. all overhead costs fixed overhead costs selling and administrative expenses variable overhead costs Knowledge Check 02 Absorption costing income statements ignore ________. direct materials and direct labor costs direct and indirect cost distinctions product and period cost distinctions variable and fixed cost distinctions Knowledge Check 03 When the number of units produced is greater than the number of units sold, variable costing net operating income will be ________. the same as absorption costing net operating income greater than absorption costing net operating income less than absorption costing net operating income Select Foods Inc. uses activity-based costing to determine product costs. For each acitivty listeed in the left column, match an appropriate activity base from the right column. You may use items in the activity-base list more than once or not at all.Activity Activity BaseAccounting reports Engineering change ordersCustomer return processing Kilowatt hours usedElectric power Number of accounting reportsHuman resources Number of customersInventory control Number of customer ordersInvoice and collecting Number of customer returnsMachine depreciation Number of employeesMaterials handling Number of inspectionsOrder shipping Number of inventory transactionsPayroll Number of machine hoursProduction control Number of material movesProduction setup Number of payroll checks processedPurchasing Number of production ordersQuality control Number of purchase ordersSales order processing Number of sales ordersNumber of setups Most mutations that cause cancer occur within body cells, and body cell mutations are not inherited. If cancer is not inherited, why does cancer statically appear to run in families? Family members have a similar genetic make-up that may make them predisposed to cancer. Family members are exposed to similar environmental conditions. Family members have a widely varied genetic make-up that can be affected by specific mutagens. Family members share the contagious mutagens that can be passed by close exposure. Can someone help me with this please??? What is 25% of 80?x=2x=75x=20 can y'all help me no pressure:)